Jan-17-2007 08:56printcomments

Oregon PUC Rejects PacifiCorp Plan to Build Two Coal Plants

In its decision, the Commission declined to resolve issues related to CO2 risk at this time.

Coal smokestack
Photo courtesy: tamu.edu

(SALEM) - The Oregon Public Utility Commission has rejected PacifiCorp’s request to conditionally approve a plan to seek bids to build two coal plants in order to meet growing energy demands. The Commission found that the company failed to justify the need to acquire the amount and type of energy resources sought. And the company’s proposal was not consistent with its earlier acknowledged resource plan. In the previously approved plan, PacifiCorp presented a preferred strategy that included short-term market purchases, renewable resources and conservation to meet growing resource demands in the eastern part of its system, primarily Utah. “In its Request for Proposals we expected PacifiCorp to fully explore strategies that would allow the company to delay a commitment for a big new central generating plant,” Commission Chairman Lee Beyer said. “It didn’t do that. We simply cannot conclude, based on the information provided to us, that it is reasonable for PacifiCorp to make a commitment of this magnitude without further study.” Commission staff argued that PacifiCorp’s request for approval of 1,109 megawatts (MW) of new generating resources overstated its energy needs. Staff analysis indicated the need for 157 (MW) in 2012 and 335 MW in 2013. The Commission agreed with staff’s analysis, and also concluded that PacifiCorp had failed to prove that base load resources are the best way to meet growing resource needs that are seasonal in nature, with the highest demand forecast for the summer months. A coalition of customer group and others had opposed the plan because it included coal generation. In its decision, the Commission declined to resolve issues related to CO2 risk at this time. However, the Commission has opened a separate proceeding to review CO2 risk related to the expected cost, risk and uncertainties of coal resources. PacifiCorp has the option to submit a new plan to the Commission. PacifiCorp is owned by MidAmerican Energy Holdings Inc. PacifiCorp serves approximately 530.000 customers in Oregon.



Related
| | |

Comments [Return to Top]
Leave a comment on this story.
Name:

Enter the text from the image to confirm you are human.(Cookies are required)


HTML tags and certain characters are removed - (numbers, letters only or post may be cut short.) certain words are banned to stop spammers. All comments and messages are approved by people and self promotional links or unacceptable comments are denied.

©2009 Salem-News.com. All opinions expressed in this article are those of the author and do not necessarily reflect those of Salem-News.com.
Articles for January 16, 2007 | Articles for January 17, 2007 | Articles for January 18, 2007
Pioneer Pacific College...better yourself
Start School NOW!

Use PayPal to
contribute to the
production of
"War and PTSD",
a Documentary:

Oregon's oldest auction family



Reach your prospects! Advertise on Salem-News.com

Montes Coins & More

Raymo Mancini's new CD is available now!
Hear Raymo's Songs